A power failure at a wastewater pumping station is difficult at any time. During prolonged or intense rainfall, inflow may already be high, storage may be limited and access routes may be under pressure. The time available to respond can shrink just as the consequence of lost pumping capacity increases.
Backup-power planning should therefore be based on the wet-weather operating case, not only a normal dry-weather load. The generator, starting system, switchgear, controls, fuel and response plan must work as one arrangement.
Quick answer: what changes during peak wet weather?
Pumps may run more frequently or together, motor-starting demand may increase, upstream storage can fill faster and emergency access may take longer. A station that appears adequately protected during a routine visit can have less margin during a storm.
Start with the consequence and response time
For each station, establish the consequence of power loss, time to an unacceptable level, available storage, overflow controls, environmental sensitivity and practical attendance time. Link these to the site's permit conditions, pollution response arrangements and escalation plan.
The result should be a clear priority category and an action trigger. A remote station with rapid level rise and poor storm access may require a different strategy from a site with greater storage and several independent pumps.
Size for the real wet-weather duty
Generator sizing must consider which pumps may operate together, their starting method, motor inrush, power factor and the auxiliary loads needed for safe control. Telemetry, control panels, screens, valves, odour control, lighting and local welfare can all add demand.
- largest credible combination of pumps in service
- direct-on-line, star-delta, soft-start or variable-speed starting behaviour
- starting sequence and time between motors
- control, telemetry and communications loads
- heating, ventilation or ancillary systems required during the event
- future pump or process changes not reflected in the original design
A generator can run normally at low load but still struggle when the first large pump starts. The planned test should represent the operating sequence closely enough to expose that risk.
Check the whole transfer path
A permanent standby set is only useful if the start signal, generator controls, ATS or switchgear and downstream distribution operate correctly. Review auto mode, inhibited starts, alarms, interlocks and remote-status signals. A successful engine start does not prove that the station has transferred or that the pumps have restarted in the intended order.
Where a site uses a temporary generator, confirm the connection point, earthing design, phase sequence, protection, switching method and cable route in advance. Connections and switching must be undertaken under the approved design and by competent authorised people.
Fuel autonomy must include storm access
Fuel planning should use a realistic consumption range at the expected duty, usable tank capacity and a reserve. It should also consider whether a tanker can reach and safely refuel the site in severe weather.
- current usable fuel rather than gauge percentage alone
- estimated consumption at the planned pump duty
- forecast duration plus an agreed contingency reserve
- supplier response and out-of-hours contact
- road closures, soft ground, gates, turning space and hose reach
- safe separation from ignition sources, water and public access
- fuel-quality history for sets that run infrequently
Pre-event refuelling can be valuable, but overfilling, spill risk and site-specific oil-storage duties still need to be controlled.
Make telemetry actionable
Telemetry should help the response team understand whether mains has failed, the generator has started, the station is on backup power and pump duty is being maintained. A generic generator alarm without site state or priority can create delay.
Useful signals may include mains failure, generator available/running/common alarm, low fuel, ATS position, pump fail, wet-well level and communications loss. Time stamps and alarm routing should be checked before the storm season, including who receives an out-of-hours event.
Inspect the physical site
- water ingress routes to generator, switchgear and control rooms
- drainage and safe equipment levels
- ventilation and exhaust condition
- access gates, locks, vegetation and delivery route
- lighting for night attendance
- external connection-point condition and labels
- cable routes that remain safe in rain and public areas
- communications coverage and alternative contact method
If floodwater could reach electrical equipment, the response must follow the site's electrical and flood safety plan. Do not enter water around energised equipment.
Test the scenario, not just the engine
Routine servicing maintains generator condition. A resilience exercise asks whether the station achieves the required outcome. Depending on site risk and permissions, this may include automatic start, transfer, pump sequence, telemetry, alarm escalation and a controlled return to mains.
Define the scope, safe conditions and acceptance criteria before the test. Where a live site test is not appropriate, combine component tests, load-bank evidence and a tabletop exercise to close as much of the assurance gap as reasonably possible.
Prepare temporary-power contingency
A temporary generator plan should identify capacity, voltage, connection, cable length, delivery route, set-down area, operating hours, fuel support, security and the authorised switching procedure. Record compatible supplier equipment and response assumptions.
Consider what happens if several stations are affected at once. Regional weather can create simultaneous demand, so prioritisation and supplier capacity matter as much as the plan for one asset.
The 48-hour pre-event check
- review forecast, priority sites and on-call coverage
- confirm generator auto mode and no unresolved critical alarms
- check starting batteries, charger, coolant, oil and visible leaks
- confirm usable fuel and refuelling plan
- test telemetry paths and contact lists
- inspect access, drainage and temporary connection points
- confirm supplier availability and temporary generator allocation
- brief the incident lead on thresholds and escalation routes
After the event
Capture run hours, loads, fuel used, alarms, transfers, call-outs and near misses. Inspect equipment that operated for extended periods and replenish fuel. Any temporary arrangement, bypass or isolated protection must have a clear removal and restoration plan.
Use the event record to update autonomy estimates, access assumptions and priority categories. Real storm evidence is especially valuable when converted into action.
Frequently asked questions
More pumps may run, motors may start more often and auxiliary systems may be needed. The resulting steady and transient demand can be higher than in dry weather.
Use the site's credible operating and failure scenarios. Pump duty, standby philosophy, starting sequence and process consequence determine the required combination.
Base autonomy on expected duty, usable tank capacity, forecast duration, reserve and realistic refuelling access. There is no single number for every station.
No. It may not prove transfer, pump restart, load acceptance, telemetry, fuel autonomy or the return-to-mains sequence.
Capacity, connection and earthing design, switching, cable route, delivery access, operating area, fuel, security, contacts and competent attendance.
Mains failure, generator running/available/common alarm, low fuel, transfer position, pump status, high level and communications loss are common priorities, subject to the site design.
Only where the equipment, method, risk assessment and site controls explicitly allow it. Fuel transfer introduces fire, spill and environmental risks.
Run hours, load, fuel use, alarms, response time, access, transfers, failures and near misses, followed by owned corrective actions.
Prepare the station before the forecast becomes an incident
Wet-weather readiness connects power capacity with pumps, controls, fuel, telemetry, access and environmental response.
Contact P&I Group to review permanent or temporary generator provision, servicing, refuelling and connection readiness for wastewater sites.
Latest news
What Happens During a Critical Power Site Survey?

Temporary Power for Planned Shutdowns: A Site-Readiness Checklist

What Signals Should a UPS or Generator Send to a BMS?

Generator Fuel Autonomy: How Many Hours of Backup Power Does Your Site Need?

How Often Should an Automatic Transfer Switch Be Tested?